To move an AI POC into production you need six things: a deployment budget, an owner, real data, integration, security and a decision date. Settle them before the test. If the test has already finished, settle them before any extension. A POC shows that an idea works. Whether it pays, and whether the company can run it, remain open questions. When these points only come up at the end of the test, a project can stop even though the technology works.
I am a go-to-market consultant for B2B tech startups, so I look at the POC from the seller's side. This page is for teams running an AI POC. Its last section is for startups selling one.
What the studies say about AI POCs
The 87% figure is often attributed to Gartner, and I have found no Gartner source for it. The articles that repeat it trace it to VentureBeat, in 2019, and it concerned data science projects. Below are three traceable sources. They measure different things, so the 30% and the 88% cannot be compared.
| Source | What it says | How to read it |
|---|---|---|
| IDC and Lenovo (2025) | 88% of the AI POCs studied do not reach large-scale deployment. Of 33 POCs launched on average, 4 reach production | A study run in partnership with a vendor, Lenovo. The article cited gives neither the sample nor the method |
| Gartner (July 2024) | At least 30% of generative AI projects abandoned after the POC by the end of 2025 | A 2024 prediction with an end-2025 deadline. No measurement behind it |
| RAND (August 2024) | By some estimates, more than 80% of AI projects fail. The most common cause is a misunderstanding of the project's purpose | Covers AI projects in general, not POCs. The 80% comes from other estimates |
The exact rate matters little. Gartner names data quality and unclear business value, the article on the IDC study names data preparation and unclear objectives, and RAND puts a misunderstanding of the project's purpose first.
Why does a successful AI POC not reach production?
This list is my own reading of the problem, with no statistics behind it. If your test has finished, apply the "What to do" column now.
| Blocker | Sign | What to do |
|---|---|---|
| Value not quantified | The test succeeds, but nobody can say what it brings in | Write down the expected gain in money, time or risk before you start |
| No deployment budget | An innovation budget paid for the POC, with nothing planned afterwards | Identify the budget line and its owner during scoping |
| Data not ready | The test runs on an extract cleaned by hand | Test on data close to reality and put a cost on preparing it |
| Integration ignored | The demonstration sits apart from the company's tools | List the systems to connect and have the IT department approve the list |
| Security and compliance arrive late | The security lead discovers the project at the end | Bring them into scoping, along with the questions on data and hosting |
| Nobody owns operations | Nobody knows who monitors the model or pays the running costs | Name an owner and estimate the monthly running cost |
| Adoption forgotten | The teams concerned have never used the solution | Have real users test it and measure their use |
What should you decide before starting the test?
Write these five decisions on one page. If one is missing, do not start the POC.
- The problem: which task changes, for whom, and which measure will show it.
- The decision-maker: the name of the person who will approve the deployment, and their budget.
- The scope: the real data used, the systems connected and what is excluded.
- The decision date: a meeting set before the start, with the decision-maker present.
- The next step: what happens if the criteria are met, and what happens if they are not.
If a supplier is involved, these points belong in the POC contract.
Which criteria decide the move to production?
On decision day, go through these four criteria.
| Criterion | Deploy if | Stop or rescope if |
|---|---|---|
| Performance | The written thresholds are met on real data | They are met only on a prepared extract |
| Value | The measured gain exceeds the estimated running cost | The gain has not been measured |
| Feasibility | IT and security have approved the integration | A blocking issue has no owner |
| Use | Test users use it without being chased | They go back to their old method |
Stopping on these criteria is a valid decision. If the POC touched neither real users nor real data, the decision of the day is about a pilot. On my Parcoor engagement, in medical cybersecurity, the POCs lasted a year and a half in total. That was too long, and I now set a decision date before the test begins.
If you are the startup selling the solution
The POC ends with a decision taken inside the customer's organisation, often by people who were absent from the test. Three things are in your hands.
- Charge for the test. A paid POC forces the customer to find a budget and a signatory.
- Prepare your contact's internal case. They have to convince their management, IT and security without you in the room.
- Write down the next step. Put the scope, the price and the decision date in the contract before the first day of the test.
The guide from POC to contract covers the sales side in detail.
Sources
- Le Monde Informatique, "Les projets IA dépassent rarement l'étape du PoC", 2 April 2025, on the IDC and Lenovo study (in French).
- Gartner, press release of 29 July 2024.
- RAND, The Root Causes of Failure for Artificial Intelligence Projects and How They Can Succeed, August 2024.
Frequently asked questions
Why do most AI POCs not reach production?
An IDC study run in partnership with Lenovo, reported by Le Monde Informatique in April 2025, found that 88% of the AI POCs studied do not reach large-scale deployment. The article cites unclear objectives, poor data preparation and a lack of in-house expertise, and IDC points to gaps in data, processes and IT infrastructure.
What is the difference between an AI POC and a pilot?
An AI POC checks that an idea works, often on a small data set and away from live systems. A pilot puts the solution in the hands of real users, in their environment, on a limited scope. Without a pilot, integration and adoption problems only surface at deployment.
Who should decide whether an AI POC goes into production?
The person who holds the deployment budget decides, with the head of the department concerned, the IT department and, if personal data is involved, the compliance lead. Identify that person before the test, because a convinced technical team cannot fund the next stage alone.
When should you stop an AI POC?
Stop an AI POC if it misses the criteria set at the start. Stop it too if no deployment budget exists on the decision date, or if the running cost exceeds the measured gain.
How long should an AI POC last?
There is no standard length for an AI POC. Set an end date and a decision date before you start. On my Parcoor engagement, in medical cybersecurity, the POCs lasted a year and a half in total. That was too long, and I now set both dates before the test begins.